This is a free, self-paced reading course for the PMP: Project Management Professional: PMI’s credential for people who lead projects rather than work on them. It is written to be read straight through, in order, before you start drilling practice questions. PMP is not a vocabulary exam: nearly every question is a scenario with several defensible-looking answers, and the skill being measured is recognizing what an effective project leader does first, or best. That judgment is built by reading situations, not by memorizing definitions, so the course spends its length on how the decisions are reasoned rather than on term lists.

This course is written to PMI’s Exam Content Outline effective July 9, 2026. That is worth saying plainly, because study material written for the previous outline under-weights Business Environment substantially, the domain carried 8% before the update and carries 26% now. The course is organized as one module per domain, in PMI’s published order, and each module carries the domain’s published weight, so the time you spend maps to the time the exam spends. Roughly 60% of the exam is set in agile or hybrid contexts, and the modules reflect that: predictive technique appears alongside adaptive practice throughout rather than being quarantined into a chapter of its own.

PMP Professional level 3 modules Domain-weighted Self-paced Free account

What the course covers

People

Module 1 · 33%

Leading and building teams: creating a shared vision, managing conflict, servant leadership, engaging stakeholders, coaching and mentoring, communication, and knowledge transfer. Every item in this domain is a human situation (a stakeholder who has gone quiet, a team in conflict, a struggling performer) and the question is always what the leader does next. The module is built around those situations because the alternative, learning the leadership vocabulary in the abstract, does not transfer to a best-answer format.

Process

Module 2 · 41%

The heaviest domain, and the technical craft of delivery across predictive, agile, and hybrid approaches: planning and estimating, scope and backlog management, schedule and critical path, earned value, quality, risk responses, procurement and contracts, and closing. Two kinds of question live here and both need practice. The calculations (SPI, CPI, EAC, float, PERT) are worked rather than read, and should come back without prompting before you sit. The method-selection items ask which approach fits a described situation, which is judgment, and is the part candidates from a single-methodology background tend to find hardest.

Business Environment

Module 3 · 26%

The domain the 2026 update more than tripled, and the one worth budgeting real time for: governance and compliance, benefits realization and value measurement, organizational change management, strategic alignment, and the external environment, plus the content areas the new outline made formally testable, sustainability and ESG, and the responsible use of AI in project management. Candidates who study this domain the way an older syllabus treated it, as a short closing chapter, are giving away a quarter of the exam.

How to use it

Read a module, then take the matching portion of the PMP practice exam rather than saving every question until the end. Testing a domain immediately after reading it is what exposes the gap between following an argument on the page and picking the best of four plausible actions under time pressure, which is the gap PMP actually measures. If you want to see the question style before committing to a full-length sitting, the free PMP sample is a short set drawn from the same bank. Module 2 is the exception to read-then-test: work the earned value and critical path arithmetic on paper until it is automatic, because those items cost time you will want for the scenarios. The course modules themselves open once you are signed in to a free Certifym account.

For exam logistics, the 180-question format with 170 scored items, the 240-minute window and its two breaks, PMI’s domain-level proficiency scoring, and the experience and education eligibility routes, see the PMP certification guide.

← Back

Earned value management and forecasting

5 min read · Free preview

Earned value management integrates scope, schedule, and cost into a single set of measures, and it is the most reliably calculable material on the exam. The formulas are few, and the questions test whether you can apply them under time pressure and interpret the result correctly.

The three base measures

  • Planned value (PV) — the authorized budget assigned to the work scheduled to be completed by a point in time. What you planned to have spent for the work you planned to have done.
  • Earned value (EV) — the budgeted value of the work actually completed. What that completed work was worth in baseline terms. Note carefully: EV is measured in budget currency, not in actual cost.
  • Actual cost (AC) — what was actually spent on the work completed.

Budget at completion (BAC) is the total cost baseline. If the project is 40% complete against a BAC of 500,000, then EV = 0.40 × 500,000 = 200,000, whatever was spent.

Variances

  • Schedule variance: SV = EV - PV. Negative means behind schedule.
  • Cost variance: CV = EV - AC. Negative means over budget.

Both follow the same shape: earned value minus the thing you are comparing it to, and negative is bad. That single sentence prevents most sign errors.

Indices

  • Schedule performance index: SPI = EV / PV. Below 1.0 is behind schedule.
  • Cost performance index: CPI = EV / AC. Below 1.0 means you are getting less than a unit of value per unit spent.

Indices are ratios and therefore comparable across projects of different size, which is why governance reports use them. CPI is the more reliable of the two: research on completed projects consistently finds that CPI stabilizes early and rarely improves afterward, which is why it is the default assumption in forecasting.

SPI has a known weakness. As a project approaches completion, all remaining work is eventually earned, so SPI drifts toward 1.0 even for a late project. A project finishing three months late will report SPI = 1.0 on its final day. For schedule status near the end, read the critical path, not the index. Where schedule performance must be tracked in time units rather than currency, earned schedule techniques exist for exactly this reason.

Forecasting

Estimate at completion (EAC) forecasts the total cost. Which formula applies depends on an assumption you must extract from the question:

  • Current variance is typical and will continue: EAC = BAC / CPI. The default and the most commonly correct.
  • The variance was a one-off; future work will run to plan: EAC = AC + (BAC - EV).
  • Future work will be affected by both cost and schedule performance: EAC = AC + [(BAC - EV) / (CPI × SPI)]. Used where recovering the schedule will itself cost money.
  • The original estimate is invalid: EAC = AC + bottom-up ETC, where the remaining work is re-estimated from scratch.

Estimate to complete (ETC) is the expected cost of the remaining work: ETC = EAC - AC. Variance at completion: VAC = BAC - EAC; negative means a forecast overrun.

The to-complete performance index (TCPI) gives the efficiency the remaining work must achieve to hit a target. Against the original budget: TCPI = (BAC - EV) / (BAC - AC). Against a revised forecast: TCPI = (BAC - EV) / (EAC - AC). Interpretation is the examinable part — a TCPI meaningfully above 1.0 when current CPI is below 1.0 means the target requires performance the project has never demonstrated, which is a signal to change the plan rather than to promise harder.

Working a question

A worked example: BAC = 800,000; at the review point PV = 400,000, EV = 350,000, AC = 380,000.

  • SV = 350,000 - 400,000 = -50,000 — behind schedule.
  • CV = 350,000 - 380,000 = -30,000 — over budget.
  • SPI = 350,000 / 400,000 = 0.875; CPI = 350,000 / 380,000 ≈ 0.921.
  • EAC = 800,000 / 0.921 ≈ 868,600 if performance continues.
  • ETC ≈ 868,600 - 380,000 = 488,600; VAC ≈ 800,000 - 868,600 = -68,600.

Read the story the numbers tell: this project is late and overspending, and on current performance will overrun by roughly 69,000. That interpretation, rather than the arithmetic, is usually what the question asks for.

Conditions and limitations

Earned value requires a scope baseline, a time-phased cost baseline, and an objective rule for measuring completion. That last condition is where it fails in practice: if progress is claimed by opinion, EV is fiction. Use rules that resist optimism — fixed formula credit such as 0/100 or 50/50 for short work packages, or physical measurement where output is countable.

In adaptive delivery, the equivalent signals are throughput, cycle time, and burnup against a scope line, and hybrid projects frequently report earned value at the control account level while the teams inside work from flow metrics. Whichever measure is in use, the discipline is the same: measure completed work objectively, forecast from demonstrated performance rather than from intention, and act on the forecast while the remaining budget still gives you options.

Reading the four combinations

Most interpretation questions reduce to one of four states, and it is worth being able to name each instantly.

  • CPI > 1 and SPI > 1 — ahead and under budget. Check that progress claims are genuine before celebrating, since inflated completion percentages produce exactly this signature.
  • CPI > 1 and SPI < 1 — under budget but late, which frequently means work has not been started rather than that it was cheap. Look for unstaffed activities.
  • CPI < 1 and SPI > 1 — ahead of schedule but overspending, typically because the schedule was bought with overtime or extra resources.
  • CPI < 1 and SPI < 1 — late and over budget, the state that most needs a re-forecast and a conversation with the sponsor rather than a recovery promise.

One further caution the exam likes: earned value tells you the size and direction of a variance, not its cause. The correct next step after computing an unfavorable index is nearly always to analyze the variance and identify the driver, not to jump to a corrective action chosen before the cause is known.

Frequently asked questions about the PMP training course

Is the PMP training course free?

Yes. The course costs nothing to read and opens once you are signed in to a free Certifym account, no payment and no card.

How is the course structured?

One module per domain of PMI’s Exam Content Outline, in PMI’s published order, with each module weighted to the domain’s published percentage: People 33%, Process 41%, Business Environment 26%. Within each module the material is broken into short lessons, followed by key terms and further reading.

Does this count toward the 35 hours of project management education?

No. PMI’s eligibility route requires 35 hours of project management education from a qualifying provider, or an active CAPM, and Certifym is not a qualifying provider. Use this course as a study companion alongside whatever training you use to satisfy that requirement, not instead of it.

Do I need project experience before starting?

For the exam, yes. PMI requires either a four-year degree plus 36 months leading projects, or a high school diploma or associate degree plus 60 months. For the course, that experience is what makes the scenarios readable rather than abstract. If you are earlier than that on the path, the CAPM course covers the same vocabulary without assuming you have led delivery.

What should I do after finishing the course?

Move to the PMP practice exam and work full-length, timed sittings rather than untimed question sets, stamina across 240 minutes is part of what fails people. Watch your Business Environment score specifically; a strong Process result can hide a weak one there. Then book with Pearson VUE.

Is the course current with the PMP exam outline?

The course is written to the Exam Content Outline effective July 9, 2026, which rebalanced the three domains, consolidated 35 tasks into 26, and added AI in project management, sustainability, and value delivery as testable content. PMI can revise the outline at any time; download the official, current Exam Content Outline from pmi.org before you sit the exam.

Trademark notice & independence. Certifym.net is operated by Certifym Exam Services, LLC and is not affiliated with, endorsed by, or sponsored by Project Management Institute, Inc. PMP®, PMI®, CAPM®, and PMBOK® are registered marks of Project Management Institute, Inc. Use of these marks is solely to identify the certification for which these study materials are intended. The PMP Exam Content Outline and its domain structure are the property of Project Management Institute, Inc.; candidates should download the official, current exam content outline directly from pmi.org.

All course content, questions, answers, and explanations on Certifym are original content created for study purposes. They are not actual PMI training materials or examination questions and are not represented as such. Studying with these materials does not guarantee a passing result on any live certification exam. Exam requirements, format, domain weights, eligibility, and pricing are set by Project Management Institute, Inc. and may change; always verify current details at pmi.org before scheduling your exam.